Mezzanine / Decking / Racking Design

Many clients and industrial property owners are now purchasing industrial B1 and B2 spaces with high void industrial production. Due the extra space, clients are building mezzanines / decking for additional storage use.

The following is legal under the following rules:

  •  If a mezzanine is <5sqm in area, no Authority submission is required as per URA guidelines. We will be able to do a PE endorsement design check and drawing for the mezzanine.
  • If a mezzanine is > 5sqm, It has to get clearance from JTC if it’s a JTC property lease, SCDF for fire safety (Fire Code 2018) and BCA for structural stability. Also URA has to be cleared to satisfy the plot ratio of the development.
  • A means of escape from the mezzanine level has to be developed via a 1m width staircase. <60sqm requires 1 staircase and for every additional 60sqm, an additional staircase is required.
  • If the building is fire sprinklered, it is compulsory for fire sprinklers to be installed below the mezzanine.
  • The mezzanine must have an area of 50% perforated flooring
  • The mezzanine must only be used for storage, office space is not allowed.

 We help our clients to design and construct new mezzanine, or even regularize due to JTC, SCDF, or BCA audits for industrial and commercial property.

Partners for decking, racking and mezzanine works
Stellar Structures in Singapore

FAQ

Do you have a standard price for Authority Submissions?
A: There is no standard price to jobs. It is based on complexity, scale, phase of works. Please contact us via Whatsapp, Telegram, Email to inquire.
What is the documents you might require to give us a Quotation?
A: Please let us know the scope of works you would like us to provide, provide any supporting reports/architectural drawings/engineering drawings.
Can you work within my budget?
A: Please do let us know if you have a budget to keep in mind based on the scope and we will try to assist to work within the budget.
What is your guarantee of completion of Authority submissions?
A: No Company can provide a 100% guarantee, and all submissions are subject to Authority Approval, however our clearance rate is currently standing at 99% Our objective is to be transparent to our clients with all the requirements to meet clearance.